Name of Assignment / Project | Start Date | Completed Date | Client | Contract Amount of Consulting Services (NRs.) | Single/ JV |
---|---|---|---|---|---|
Cadastral Survey of Chuniya - Namtar - Kalikatar - Bharta - Khairang Road (Chainage: 0+000 to 20+235) (Length: 20.235 Km) | 27 Nov. 2016 | 22 Feb. 2017 | District Coordination committee Makawanpur, DTO, Hetauda |
2,28,655.50 (Inclusive of VAT) |
Single |
Feasibility Study of Various Regional and Tourism Roads and report preparation of Package No.: PMEU/337159/071/72 F1 as followings roads:
|
20 June, 2015 (2072-03-06) | 10 Oct., 2015 (2072-06-24) | Department of Roads, Planning & Design Branch | 14,99,400.00 (Excluding VAT) | ECoCoDE-Rajdevi-E.C.N. |
Feasibility Study of Various Regional and Tourism Roads and report preparation of Package No.: PMEU/337159/071/72 F11 as followings roads:
[Total Length of the Roads 133.43 Km] |
20 June, 2015 (2072-03-06) |
1 Oct. 2015 (2072-06-15) | Department of Roads, Planning & Design Branch |
22,45,000.00 (Excluding VAT) |
ECoCoDE-Rajdevi-E.C.N. |
Detailed Engineering Survey, Design and Cost Estimate, DPR (Detailed Project Report) of Piparpati – Bariya – Kotwali Road[Length of Road 8.025 Km] |
2072/1/23 | 2072/3/24 | District Technical Office, Bara | 2,93,811.30 | Single |
Manual Traffic Volume Count At HetaudaNarayangad Road, Contract Identification No: RBN - 2071/072/02 Traffic Count HN Road. |
29 Sept. 2014 | 28 Nov. 2014 | Roads Board Nepal | 2,23,175.00 (Including VAT) | Single |
Detail Engineering Survey, DCP Test, Design of Roads, Concise IEE Study and Preparation of DPR of Ugratara- Melauli Road,Dadhildhura (78.504 Km) and Bhortola- Jojivi- Shera Road, Darchula (45.497 Km) [Total Length of Roads 124.001 Km] |
11 June 2013 (2070/02/28) | 09 July, 2014 (2071/03/25) | Department of Roads, Planning & Design Branch | 7,948,464.00 | SILT – GRID - RajdeviJV |
Detailed Engineering Survey, Design, Drawings and Estimate of Hilsa – Simikot Road in Humla District (Chainage 45+000 to 59+000, Total 15 KmLength). |
17 Oct. 2013 (2070/06/31) | 14 Nov., 2013 (2070/07/29) | DoR, Hilsa-Simikot Road Project, Humla | 9,33,380.00 | Single |
Detail Survey & Design Work of Rupani – Gaighat Road (Chainage 006+000 to 12+000 Km) (Length in 6 Km) in Saptari District of Nepal. |
22 Apr., 2013 (2070/01/10) | 29 June, 2013 (2070/03/15) | DDC, Saptari, Rajbiraj | 2,99,337.00 | Single |
Preparation of Detail Survey with study for KMC Ward No. 12 Pachhali Road (Pachali to Kalopul) & New Plaza – Bansghari, Anamnagar Mode. |
4 Mar., 2013 (2069/11/21) | 2 May, 2013 (2070/01/20) | District Commissioner Office, Anamnagar, Kathmandu | 2,36,706.75 | Single |
Detailed Engineering Survey, Design, Drawings and Estimate of Hilsa – Simikot Road in Humla District ((Chain- age 30+000 to 44+000 (15 Kmin Length). |
13 Mar., 2013 (2070/01/31) | 12 Jun, 2013 (2070/02/30) | DoR, Hilsa-Simikot Road Project, Humla | 9,33,380.00 | Single |
Detail Engineering Survey and Detailed design of Barabise - Duskan – Piskar - Kharidunga Road (4.4 Km Length). | 26 Sept., 2012 (2069/06/10) | 9 Dec., 2012 (2069/08/24) | Charikot Division Road under DoR | 2,49,040.00 | Single |
Detailed Engineering Survey and Detail Design of(Total Length of16.5 Km) Roads:
|
9 Apr., 2012 (2068/12/27) | 5 Jul., 2012 (2069/03/21) |
DoR, Harkapur - Okhaldhunga Road Project, Okhaldhunga |
7,81,225.50 | Single |
Detailed Engineering Survey & Design Works on Barabise - Bhairabkunda Road (Chainage 0+000-4+500 (Length 4.45 Km). | 12 Jan., 2012 (2068/09/28) | 6 Apr., 2012 (2068/12/24) | DoR, Division Road Office, Charikot, Dolakha | 2,49,200.00 | Single |